Apart from club sessions, courts may be booked in advance, click
.
Please note that these bookings are on a separate website. They can be viewed without a login,
but require a separate login in order to make or edit a booking.
If you don't have a username and password for this please ask Simon Hathrell.
Investigation begins into the feasibility, cost and options for an automatic irrigation system. A review of boreholes in the general area suggests that using a borehole at the club instead of mains water would be preferable on environmental grounds, and although it would entail a higher capital cost the pay-back in terms of saving on water bills should be within about 10 years at current mains water tariffs.
Information and advice about irrigation system design options is obtained from several other croquet clubs with irrigation systems, which are all very willing to share the information.
Written confirmation is obtained from both Affinity Water and the national Environment Agency that they have no objections to the use of a borehole for water supply at our location, and that for our expected consumption volume (under 20m3 per day) an extraction licence is not required.
Plans for an irrigation system at the club are developed. The system would be funded from a combination of existing club funds and a campaign to obtain some grants and donations.
A hydrogeological survey is commissioned for a possible borehole to supply the water. The survey reports that the local geology is favourable, with underlying chalk that should facilitate an ample supply of water with the water table expected at a depth of 15 to 20 metres.
Tenders are invited from a selection of borehole contractors.
The winning bidder is selected: Smith & Webb, a local firm.
Approval for the installation of an automatic irrigation system at the club is agreed by Watford Borough Council, subject to formal planning permission. The agreed project includes digging a borehole and the installation of above-ground storage tanks if these are also required, though the latter will depend on the water supply available from the borehole.
An application for planning permission is submitted, and published by the Council.
Some local residents make a formal objection to the proposal on the grounds that the pop-up sprinklers will make too much noise. The proposal therefore requires a full Council planning meeting for consideration.
Tuesday 6th February 2024
The objectors and the club each have an opportunity to make representations about the project at a Council planning meeting. The club points out that years ago the Council itself installed an automatic irrigation system at the bowls club nearby in the park, with sprinklers used routinely at 4am, and there have never been any complaints about the noise.
The Councillors agree at the meeting that our project can go ahead, but subject to the restriction that the sprinklers may not be used between 11pm and 7am.
Thursday 8th February 2024
The written planning approval is received from the planners with a couple of stipulations: that the work cannot start until there is also a Tree Protection Plan, and that there is adequate noise installation for the borehole pump.
A Tree Protection Plan is developed and discussed with the planners, and evidence is collected to demonstrate that the borehole pump will be completely inaudible in use, but approval requires submission of a further formal Discharge of Conditions planning application.
Acceptance of the Discharge of Conditions planning application is received, and work can finally proceed.
Work on drilling the borehole starts.
Use the buttons below each photo to step through the set, or to cycle through them all automatically.
The going is quite slow at first through a layer of gravel below the top metre of soil, but the expected chalk strata is reached after about 9m and then progress is much more rapid. The water-table is reached at a depth of 14m, consistent with the 15 to 20m predicted in the hydrogeological survey. The plan is to drill about 30m below the water-table.
Drilling continues with quite rapid progress through the chalk. The area around the borehole turns white with chalk slurry!
Drilling is completed and a 5" diameter perforated plastic pipe is inserted into the borehole.
The drilling rig is removed and the manhole pit is prepared.
The borehole supply is tested. After an hour of pumping at around 3m3/hour the water-table dropped only 60cm - a healthy supply. It started very chalky but became steadily clearer over time, which is quite normal.
The next stage is to finalise the details of the irrigation system design to suit the new water supply, and specifically the flow rates and pressures, so that an appropriate model of borehole pump can be selected and installed.
The Grundfos pump is installed at the bottom of the borehole.
The trenches for the pipes and cables are dug around all the courts, and work starts on laying the pipes and cables in them.
The pipes are installed and connected up, and work starts on digging pits for the Rainbird pop-up sprinklers, connecting up the electrics, testing the electrical connections, and then refilling the trenches, apart from above the pipe connections.
The borehole pump is connected up to the pipe network, the pressure vessel is installed inside the pavilion, and the network is checked for leaks so that the trenches around all the pipe connections in the trenches can then be refilled as well.
The sprinklers are tested, and work starts on connecting the cables to the Rainbird controller.
Automatic late-evening irrigation is started, and runs between 8pm and 11pm. The sprinkler settings and schedules are fine-tuned. The courts are fertilised and watered.
Several club members help to clear way the large amounts of stones and soil left behind by the trenches after they were refilled. The pressure vessel inside the pavilion is boxed in and the box is painted.
1200 litres of fine loam topsoil are delivered to fill the top inch of the ground above the trenches in preparation for re-seeding, and the re-seeding is started.
The club holds a 'sprinkler party' to celebrate the successful completion of the project. The courts are now green and uniformly paced, and they can now be cut to 5mm on a regular basis.