Click on images for an enlargement

Use the buttons below each photo to step through the set, or to cycle through them all automatically.

Friday 22nd September

The original state.

Monday 25th September - Day 1

Fence between court 3 and new court 4 area removed.

Day 2

Long grass removed from new court 4 area.

Day 3

Laser-surveying the levels.

Days 4-6

Work paused while an issue over the levelling of court 3 is resolved.
Underground concrete foundations for former tennis court net-posts come to light in the new court 4 area.

Tuesday 3rd October - Day 7

The top 2 cm of soil is removed by a Koro machine.
The former tennis court net-post foundations cause some trouble.

Days 8-10

No activity.

Monday 9th October - Day 11

Deeper excavation on court 3 - removing the next 10cm of soil.

Day 12

Levelling court 3. Two concrete tennis net-post foundation blocks now removed.

Day 13

Deeper excavation on court 4. Four more concrete tennis net-post foundation blocks removed.

Day 14

More levelling work. Some temporary fencing added around the court 4 area.

Day 15

More levelling work on both courts.

Monday 16th October - Day 16

Replacing the original topsoil. 3 hours lost with a burst hydraulic hose.

Day 17

Spreading the first batch of replaced topsoil and levelling with the Laser Grader.

Day 18

Remainder of court 3 topsoil replaced, but further work limited by a heavy rain shower.

Days 19-21

Too damp for further earthworks.